DE Jobs

Search from over 2 Million Available Jobs, No Extra Steps, No Extra Forms, Just DirectEmployers

Job Information

Johnson Controls Project Lead in Bengaluru, India

Project Lead/ Engineers

Responsibility

Expectations

Supervision of installation as per approved drawings

Ensure cable/conduit route, device, panel locations are as per approved drawings. Drawing revision number should be final revision.

Supervision of quality work

Ensure the laying of cables/conduits and installation of devices are as per quality standards during execution itself. Coordinate with Quality team for regular audits

System knowledge

Hands on experience with Installation, testing & Commissioning of CCTV, Access, BMS, Fire alarm Systems, Networking Etc. Fire Hydrant & Gas supersession experience is advantage for us.Certifications for Commissioning of Security and Fire detections systems.

Project Management

Hands on experience in Project Management, Vendor Management for Industrials, Pharma & Healthcare industries

Review & Approval

Review the project scope, tender along with manager Highlight the Risk & challenges. Review the costing in line with project scope, technical specifications. Have the complete understanding of solution offered.

Preparation of Project schedule

Prepare project schedule with clearly defined critical path and milestone and highlight clearance required from customer

Resource and subcon deployment

Ensure competent resources are deployed at site to handle project effectively. Efficient and competent subcon with adequate manpower is deployed to meet the project timeline

Monitoring site Progress - Planned Vs Actual

Review the design and construction progress with design and project team weekly and may be daily depending on volume and complexity of the project. Site walk with Project engineer to monitor the site progress in line with schedule

Quality check and audits

During site walk check for quality of installation. Ensure audits done parodically and findings are addressed on immediate basis. Ensure project engineer do not repeat the findings of audit.

VO management

Create VO opportunity , tender / Non tender / Time extension cost escalation. VO of 10-15% project value

Site meetings

Be part of site meetings, Raise the alerts for dependencies or clearance which may impact our project deliveries. Escalate to next level of PMC/customer if dependencies are not getting cleared

Coordination with cross functional team like design , SCM,L&D, Quality & finance

Coordinate with internal stake holders to ensure project deliveries are met. Highlight to next level in organization if any support required to ensure project timelines are not hampered.

Maintain Project Cash Flow - UBR/Collection/VO

Timely invoicing / AR collection/VO. Push for VO with site team. Account statement is maintained for each project.

Project completion and hand over

recommissioning check to be done before T&C. Ask for any technical or resource support to ROM/AOM in advance. Start preparing O&M, As built, manual during Pre-commissioning stage only.

DirectEmployers